When trying to get DOS and PDOS from a HSE calculation, I get the message: DOS, PDOS is not evaluated fro NPAR =/1, try NPAR = 1.
If I try NPAR = 1, I get: HSE cannot be run with NPAR = 1.
Is there a way out?
While at DOS/PDOS: is there a way to control the broadening applied in calculating them?
Peter
DOS/PDOS with HSE
Moderators: Global Moderator, Moderator
-
- Newbie
- Posts: 5
- Joined: Fri Nov 19, 2010 2:29 pm
DOS/PDOS with HSE
Last edited by deak on Sun May 06, 2012 9:03 pm, edited 1 time in total.
-
- Administrator
- Posts: 2921
- Joined: Tue Aug 03, 2004 8:18 am
- License Nr.: 458
DOS/PDOS with HSE
please choose LORBIT >=10, NPAR=1 is only needed if the projectors are calculated within the vasp-run itself